Problems

  1. As part of a major development, a stream crossing must be constructed at river mile 14.785 of the lower reach of the East Grand Fork River, which is shown in the figure.
  2. Click here for larger image

    English Units - Cross-section geometry data for the reach without the proposed bridge is provided in the file Prob6_1eng.g01 on the CD-ROM accompanying this text. The channel discharge for the 100-year storm event between river miles 14.43 and 16.16 is 25,660 ft3/s. A tributary adds 3290 ft3/s at river mile 14.13. The flow regime is subcritical, and the starting water surface elevation at river mile 12.59 is 450.00 ft. For the existing condition (no bridge), answer the following questions.

    1. What is the computed water surface elevation at river mile 14.43?
    2. What is the average velocity in the main channel at river mile 15.73?
    3. How much head loss due to friction occurs between river mile 13.86 and 13.98?
    4. What are the left overbank, main channel, and right overbank conveyances at river mile 14.43?
    5. What is the energy grade elevation at river mile 13.03?
    6. What is the energy correction factor (a) at river mile 14.79?
    7. SI Units - Cross-section geometry data for the reach without the proposed bridge is provided in the file Prob6_1si.g01 on the CD-ROM accompanying this text. The channel discharge for the 100-year storm event between river miles 14.43 and 16.16 is 726.7 m3/s. A tributary adds 93.2 m3/s at river mile 14.13. The flow regime is subcritical, and the starting water surface elevation at river mile 12.59 is 137.2 m. For the existing condition (no bridge), answer the questions above.

  3. English units - Add the data describing the proposed bridge at river mile 14.785 to the channel reach from problem 6.1. The roadway deck elevation of the crossing will be 462.0 ft, and the low chord elevation will be 459.0 ft along the entire length of the bridge. The roadway deck will be 48 ft wide, and the distance from the deck to the upstream cross section should be taken as 1 ft. A weir coefficient of 2.6 should be used.
  4. Two 5 ft diameter circular piers will be used to support the structure, and they will be located at cross-section stations 320.0 ft and 433.0 ft. The structure will also have sloping abutments, which are described by the data in the following table. Assume that the bridge geometry is the same for the upstream and downstream ends of the structure.

    Left Abutment
    Right Abutment
    Station, ft
    Elevation, ft
    Station, ft
    Elevation, ft
    0
    459
    480
    446
    250
    459
    519
    459
    277
    450
    800
    459

    SI units - Add the data describing the proposed bridge at river mile 14.785 to the channel reach from problem 6.1. The roadway deck elevation of the crossing will be 140.8 m, and the low chord elevation will be 139.9 m along the entire length of the bridge. The roadway deck will be 14.6 m wide, and the distance from the deck to the upstream cross section should be taken as 0.3 m. A weir coefficient of 1.44 should be used.

    Two 1.5 m diameter circular piers will be used to support the structure, and they will be located at cross-section stations 97.5 m and 132.0 m. The structure will also have sloping abutments, which are described by the data in the following table. Assume that the bridge geometry is the same for the upstream and downstream ends of the structure.

    Left Abutment
    Right Abutment
    Station, m
    Elevation, m
    Station, m
    Elevation, m
    0.0
    139.9
    146.3
    135.9
    76.2
    139.9
    158.2
    139.9
    84.4
    137.2
    243.8
    139.9

    Left and right ineffective flow area boundaries must be defined for the cross sections immediately upstream and downstream of the bridge. It is recommended that the initial elevation of the upstream ineffective flow areas be taken as equal to the low point of the road, and the initial elevation of the downstream ineffective flow areas be taken as equal to the low chord elevation. Complete the worksheet below to select the stationing for the upstream and downstream encroachments assuming a 1:1 contraction ratio and a 3:1 expansion ratio. If there is a significant difference between assumed water surface elevations and computed water surface elevations (and thus a significant difference in top width of flow due to the sloping abutments), multiple iterations may be required to arrive at final encroachment stations.

    Upstream Side of Bridge
    Left
    Right
    Distance from R.M. 14.79 cross section to bridge face
       
    Assumed water surface elevation at upstream bridge section
       
    Cross-section station where assumed water surface intersects bridge abutment
       
    Assumed encroachment stations
       
    Computed water surface elevation at upstream bridge section
       
    Final encroachment stations
       

    Downstream Side of Bridge
    Left
    Right
    Distance from bridge face R.M. to 14.78 cross section
       
    Assumed water surface elevation at downstream bridge section
       
    Cross-section station where assumed water surface intersects bridge abutment
       
    Assumed encroachment stations
       
    Computed water surface elevation at downstream bridge section
       
    Final encroachment stations
       

  5. The agency responsible for floodplain management has stressed that the stream crossing from problem 6.2 must not cause any adverse affects to the hydraulics of the stream system. Perform analyses using each the following bridge modeling approaches and record the results in the table provided.
    1. Energy method
    2. Momentum method option
    3. Yarnell's equation
    4.  
      Energy Method
      Momentum Method (Cp = _____)
      Yarnell's Equation (K = _____)
      Increase in water surface elevation at R.M. 14.79 (compared to Problem 6.1)
           
      Most upstream cross section showing increase in water surface elevation
           
      Velocity of water through bridge
           
      Energy loss through bridge
           
      Friction loss through bridge
           

  6. The agency responsible for floodplain management of the stream has asked you to design a structure that produces no increase in the water surface elevation upstream of the bridge. Do you believe this is possible? If so, how might it be accomplished?

Haestad Methods, Inc.
www.haestad.com
Voice: +1-203-755-1666
Fax: +1-203-597-1488
info@haestad.com

www.haestad.com